Bertschi AG, a renowned Swiss transport company, specializes in providing logistics and transport services for the chemical industry. Established in 1956 and headquartered in Durrenasch, Switzerland, Bertschi is a member of the European Chemical Transport Association. With over 60 subsidiaries in Europe, the Middle East, Asia, and the United States, the company generates an average annual revenue of more than 700 million US dollars. Its four main business divisions employ more than 2,700 people worldwide.
In 2012, Bertschi entered the Chinese market, partnering with Sinokap to deliver professional IT services. In February 2023, Bertschi’s headquarters IT team initiated the Network Migration Project for their Shanghai office. Sinokap successfully provided technical support, earning the client’s satisfaction.
After extensive communication with Bertschi’s headquarters IT team, we developed a stringent and secure upgrade plan, which we completed successfully. In this case study, we’ll delve into the details of the project and discuss why a comprehensive and meticulous plan was necessary.
1. Network Physical Topology Chart Planning and Design:
Establishing port connections early in the process saves time and communication costs during construction and helps identify any missing special modules or jumpers.
2. IT Rack Planning and Design:
Due to the complex on-site working environment, planning the location of all equipment in advance allows construction workers to build according to the drawings.
3. PDU (Power Distribution Unit) Planning and Design:
Calculating each device’s power consumption is crucial to ensure sufficient power supply for the entire IT room.
4. Backup of Existing Network Devices:
A thorough backup of existing equipment ensures the old equipment can be replaced if there are problems with the new equipment.
5. Hardware Detection of New Network Devices:
Early power-on inspections guarantee that the equipment starts normally and hasn’t been damaged during transportation.
The following steps detail the on-site construction process:
1. Remove old network equipment
2. Install new network equipment
3. Manage and adjust network drop cable
4. Cooperate with configuration and testing
5. Clean IT room
A clear completion checklist is essential to quickly confirm the successful completion of the IT upgrade.
A quick recovery plan ensures that the company’s business can continue to operate normally in case of upgrade issues.
The support and understanding of all employees contribute to a smoother project. Informing employees about the project’s impact on their work is vital.
Sinokap is committed to treating each customer’s IT project with seriousness and responsibility. We ensure the stable, safe, and reliable operation of company networks and maintain the IT room environment. If your company suffers from an unstable network, please contact us!
Call Us, Write Us, Or Knock On Our Door. We are here to help. Thanks for contacting us!
Subscribe now to keep reading and get access to the full archive.